Friday, July 20, 2012

A.Lamp completed the sidewalk removal and replacements this week.

Next week, the contractor anticipates completing the underground utility spot repairs.

Manhole repairs in the parkway will be completed in conjunction with the sod restoration work during the fall.

The road resurfacing is may begin later next week. Residents will be notified prior to this work beginning.

Sewer televising and cleaning crews also been on-site, this work is in conjunction with a sewer lining project within the Village.