Friday, June 1, 2012



The contractor completed concrete curb & gutter, driveways, and sidewalks on the south side of the roadway this week. Access to driveways is expected to be restored on Saturday, June 2nd. Thank you for your patience and cooperation.

The contractor anticipates asphalt patching the aggregate trenches along Joanne Drive. Driveway access to residents on the north side of the roadway will be limited during excavation and paving operations.  If you reside on the north side of Joanne, please have cars removed from your driveways by Monday, June 4th at 7:00 AM.  Access to your driveway will be restored later in the day Monday.  Driveways on the south side of the street will not be affected.