Friday, August 31, 2012

The roadway work was completed as part of the Village’s 2012 Resurfacing Project.

Manhole repairs in the parkway will be completed in conjunction with the sod restoration work during the fall.

Saturday, August 25, 2012

The roadway work was completed last week as part of the Village’s 2012 Resurfacing Project.

Manhole repairs in the parkway will be completed in conjunction with the sod restoration work during the fall.

Saturday, August 18, 2012

The underground utilities portion of the work is completed. The roadway work has begun as part of the Village’s 2012 Resurfacing Project.

The new asphalt pavement is expected to be completed the week of August 20th.   

Manhole repairs in the parkway will be completed in conjunction with the sod restoration work during the fall.

Friday, August 10, 2012

The underground utilities portion of the work is completed. The roadway work has begun as part of the Village’s 2012 Resurfacing Project.

The new asphalt pavement is expected to be completed next week.

Manhole repairs in the parkway will be completed in conjunction with the sod restoration work during the fall.

Friday, August 3, 2012

The underground utilities portion of the work is completed. The roadway work has begun as part of the Village’s 2012 Resurfacing Project.

This week the existing pavement was removed. The new asphalt pavement is expected to be installed next week.

Manhole repairs in the parkway will be completed in conjunction with the sod restoration work during the fall.

Friday, July 27, 2012

This week A. Lamp contractor completed the underground utility spot repairs.

Manhole repairs in the parkway will be completed in conjunction with the sod restoration work during the Fall.

The roadway pavement removal is scheduled for this Tuesday. Residents will be notified prior to this work beginning. This work is part of the Village’s 2012 Resurfacing Project.

Friday, July 20, 2012

A.Lamp completed the sidewalk removal and replacements this week.

Next week, the contractor anticipates completing the underground utility spot repairs.

Manhole repairs in the parkway will be completed in conjunction with the sod restoration work during the fall.

The road resurfacing is may begin later next week. Residents will be notified prior to this work beginning.

Sewer televising and cleaning crews also been on-site, this work is in conjunction with a sewer lining project within the Village.