Friday, October 5, 2012

Work Completed - Last Blog Post

The project is now completed.

This is the last blog update that will be provided for this project.

We appreciate you taking the time to read this blog.

We hope this was a valuable resource for you following the progress of work completed and what work was scheduled in the coming weeks.

Thank you again for all of your patience throughout the construction season.

If you have any outstanding issues that you need addressed, please contact the Project Manager, Andrew Mayes, at 847-904-4410

Monday, October 1, 2012



A.Lamp completed sod restoration, manhole repairs, and miscellaneous other work in the parkway last week.

The project is nearly complete. The only remaining items are minors repairs.

Thank you again for all of your patience during this construction season.

Friday, September 21, 2012


A.Lamp started grading and installing topsoil in preparation for installing sod this week.

Next week the contractor will perform manhole repairs in the parkways and perform other miscellaneous repairs. 

Next week the contractor is also scheduled to begin installing sod on Wednesday.

Friday, September 14, 2012

A.Lamp is anticipating to perform manhole rehabilitation within the parkways next week.

Following manhole repairs, landscape restoration with sod will commence.
A.Lamp is anticipating to perform manhole rehabilitation within the parkways next week.

Following manhole repairs, landscape restoration with sod will commence.

Friday, September 7, 2012

Now that we are entering the more favorable growing season, sod restoration will begin in the near future.  Manhole repairs in the parkway will be performed during sod restoration work.

Thank you for your patience.

Friday, August 31, 2012

The roadway work was completed as part of the Village’s 2012 Resurfacing Project.

Manhole repairs in the parkway will be completed in conjunction with the sod restoration work during the fall.

Saturday, August 25, 2012

The roadway work was completed last week as part of the Village’s 2012 Resurfacing Project.

Manhole repairs in the parkway will be completed in conjunction with the sod restoration work during the fall.

Saturday, August 18, 2012

The underground utilities portion of the work is completed. The roadway work has begun as part of the Village’s 2012 Resurfacing Project.

The new asphalt pavement is expected to be completed the week of August 20th.   

Manhole repairs in the parkway will be completed in conjunction with the sod restoration work during the fall.

Friday, August 10, 2012

The underground utilities portion of the work is completed. The roadway work has begun as part of the Village’s 2012 Resurfacing Project.

The new asphalt pavement is expected to be completed next week.

Manhole repairs in the parkway will be completed in conjunction with the sod restoration work during the fall.

Friday, August 3, 2012

The underground utilities portion of the work is completed. The roadway work has begun as part of the Village’s 2012 Resurfacing Project.

This week the existing pavement was removed. The new asphalt pavement is expected to be installed next week.

Manhole repairs in the parkway will be completed in conjunction with the sod restoration work during the fall.

Friday, July 27, 2012

This week A. Lamp contractor completed the underground utility spot repairs.

Manhole repairs in the parkway will be completed in conjunction with the sod restoration work during the Fall.

The roadway pavement removal is scheduled for this Tuesday. Residents will be notified prior to this work beginning. This work is part of the Village’s 2012 Resurfacing Project.

Friday, July 20, 2012

A.Lamp completed the sidewalk removal and replacements this week.

Next week, the contractor anticipates completing the underground utility spot repairs.

Manhole repairs in the parkway will be completed in conjunction with the sod restoration work during the fall.

The road resurfacing is may begin later next week. Residents will be notified prior to this work beginning.

Sewer televising and cleaning crews also been on-site, this work is in conjunction with a sewer lining project within the Village.

Friday, July 13, 2012

There was no work on-site during this past week.

The contractor still has some miscellaneous items to complete in the coming weeks including completion of underground utility spot repairs, manhole repairs in the parkways, and sidewalk removal and replacement.  

Due to the dry weather  and excessive heat conditions, the contractor will not  be installing sod at this time.  Sod is not anticipated until the fall when the weather is more favorable.

Please keep in mind the roadway will be resurfaced this summer as part of the 2012 Road Resurfacing Project.

Friday, July 6, 2012

A.Lamp Concrete Contractors completed mailbox repairs last week.

There was no work on-site during this past week.

The contractor still has some miscellaneous items to complete in the coming weeks including completion of underground utility spot repairs, manhole repairs in the parkways, and sidewalk removal and replacement.

Due to the dry weather  and excessive heat conditions, the contractor will not  be installing sod at this time.  The contractor will perform some grading of the disturbed landscape, but sod is not anticipated until the fall when the weather is more favorable for growing sod.

Please keep in mind the roadway will be resurfaced this summer as part of the 2012 Road Resurfacing Project.

Friday, June 29, 2012

A.Lamp Concrete Contractors has some miscellaneous items to complete in the coming weeks including completion of underground utility spot repairs, manhole repairs in the parkways, sidewalk removal and replacement, and repairing damaged mailboxes.

Due to the dry weather conditions, the contractor will not  be installing sod at this time.  The contractor will perform some grading of the disturbed landscape, but sod is not anticipated until the fall when the weather is more favorable for growing sod.

Please keep in mind the roadway will be resurfaced this summer as part of the 2012 Road Resurfacing Project.

Happy 4th of July.

Friday, June 22, 2012

A.Lamp Concrete Contractors has some miscellaneous items to complete in the coming weeks including completion of underground utility spot repairs, manhole repairs in the parkways, sidewalk removal and replacement, and repairing damaged mailboxes.

Due to the dry weather conditions, the contractor will not  be installing sod at this time.  The contractor will perform some grading of the disturbed landscape, but sod is not anticipated until the fall when the weather is more favorable for growing sod.

Please keep in mind the roadway will be resurfaced this summer as part of the 2012 Road Resurfacing Project.

Friday, June 15, 2012

Work remaining to be completed includes rough grading of disturbed areas, complete underground utility repairs, and sidewalk removal and replacement.

Due to the dry weather conditions, the contractor does not anticipate installing sod at this time.  The contractor will perform some grading of the disturbed landscape, but sod is not anticipated until the fall when the weather is more favorable for growing sod.

Please keep in mind the roadway will be resurfaced as part of the 2012 Road Resurfacing Project later in the year.

Friday, June 8, 2012


The contractor installed the temporary pavement patch along the north side of the roadway and street crossings.

Next week, the contractor will be on-site to perform a few underground utility repairs and landscape restoration.

Please keep in mind the roadway will be resurfaced as part of the 2012 Road Resurfacing Project later in the year.

Friday, June 1, 2012



The contractor completed concrete curb & gutter, driveways, and sidewalks on the south side of the roadway this week. Access to driveways is expected to be restored on Saturday, June 2nd. Thank you for your patience and cooperation.

The contractor anticipates asphalt patching the aggregate trenches along Joanne Drive. Driveway access to residents on the north side of the roadway will be limited during excavation and paving operations.  If you reside on the north side of Joanne, please have cars removed from your driveways by Monday, June 4th at 7:00 AM.  Access to your driveway will be restored later in the day Monday.  Driveways on the south side of the street will not be affected.