Friday, April 27, 2012

A. Lamp Concrete Contractors continued water main installation on Joanne Drive this week from Pfingsten Road to the cul-de-sac at the west end of Joanne Drive.  The contractor is scheduled to test and chlorinate the water main early next week.  Additionally, the contractor is scheduled to begin existing storm sewer and sanitary sewer repairs. 

Friday, April 20, 2012

CONSTRUCTION HAS BEGUN

Late this week A.Lamp Concrete Contractors began construction on Joanne Drive.  The contractor began work on Wednesday by grinding out the existing pavement over the proposed water main trench.  Thursday they began installing water main  at the intersection of Joanne Drive and Pfingsten Road.  The contractor is scheduled to continue installation of water main towards the west next week.

Monday, April 9, 2012

Construction season is just around the corner.

Residents are invited to attend a preconstruction meeting at the Village of Glenivew Police Department Community Room on Tuesday, April 10, 2012 from 6:00 pm to 7:00 pm.